Several precautions for debugging and checking the installation of dissolved air flotation

Before installing the equipment, it is necessary to use good concrete to lay a good foundation, and the installation can also be completed through an overhead system, but it must be able to bear the weight of the equipment during operation.
The dissolved air flotation machine needs to lay a special cleaning sewer, which is connected to the regulating tank through a pipeline, so as to discharge the waste water in time. The waste water needs to be connected between the inlet and the reaction tank. The link distance should be as short as possible to avoid flocs Broken in the pipe, the clean water outlet can be connected to the clean water tank. At the same time, the outlet of the suspended matter can be connected to the sludge thickening tank to treat the sewage through the sludge dehydrator.

Before debugging the air flotation machine, all impurities and welding slag in the cleaning tank need to be removed, and the air compressor and other parts need to be lubricated; turn on the power, start the dissolved air pump, and check whether the rotation of the equipment is consistent with the direction of the arrow.
Turn on the air compressor by hand, and then check whether the air compressor is running normally. If there is a failure, find out the cause in time; press the switch of the truss type slag scraper. Then push the surface of the scraper back to the sludge tank, turn the scraper up during this process, and press the stop button at the same time to stop scraping, keep the drug delivery device in a proper state, and separate the sewage from the suspended matter.