Operation management precautions during shallow air flotation debugging are as follows:
(1) Before debugging water inlet, first use compressed air or high-pressure water to repeatedly blow out the pipes and dissolved air tank until there are no particulate impurities that are easy to block, and then install the dissolved air releaser.
(2) A one-way valve should be installed on the air inlet pipe to prevent pressurized water from pouring into the air compressor. Before commissioning, check whether the direction of the one-way valve on the pipeline between the dissolved gas tank and the air compressor is pointing toward the dissolved gas tank. In actual operation, after the outlet pressure of the air compressor is greater than the pressure of the dissolved gas tank, the valve on the compressed air pipeline is opened to inject air into the dissolved gas tank.
(3) First use clean water to debug the pressure dissolved gas system and dissolved gas release system, and then inject sewage into the reaction tank after the system operates normally.
(4) The water outlet valve of the pressure dissolved gas tank must be fully opened to prevent the water flow from being blocked at the water outlet valve and allow the bubbles to be released and merged in advance.
(5) Control the water outlet regulating valve or adjustable weir plate of the air flotation tank to stabilize the water level of the air flotation tank at 5 to 10 cm below the slag collecting tank. After the water level is stable, use the inlet and outlet valve to adjust and measure the treated water volume until the design water volume is reached.
(6) After the scum accumulates to 5 to 8 cm, start the slag scraper to scrape the slag and check whether the scraping and slag discharge are normal and whether the effluent quality is affected.
Shallow air flotation uses tiny bubbles released from dissolved water to bring suspended solids or oil to the surface to complete the separation work. Its functions are diverse, so it is important to do regular maintenance. Here are some ways.
1. The shallow air flotation sludge valve is opened every two days. After the sludge is discharged, the valve is closed.
2. After the rotating support has been running for 100 hours, the bolt pre-tightening force should be checked every 400 hours to ensure sufficient pre-tightening force; when rotating, add oil every 100 hours and keep records. The tooth surface should be regularly cleaned of debris and coated with corresponding grease.
3. After the walking frame and scum tube inorganic transmission has been working for 500 hours, replace it with new oil and clean the internal oil dirt; in the second stage, it is 1,000 working hours; in the third stage, after 2,000 working hours, it is replaced every 2,000 hours. Check the oil level regularly and keep the oil level at the center line of the oil mark.
4. Bearings with shallow air floatation should be filled with synthetic calcium-based grease once a month.