Installation, debugging and precautions for dissolved air flotation equipment

1. The foundation of dissolved air flotation equipment must be laid before installation. And use concrete mortar to pad the height by 100-150mm. It can also be installed overhead, but the foundation must be able to bear the weight of the equipment during operation.

2. The level of the equipment needs to be adjusted after it is in place.

3. The equipment needs to be equipped with a sewer for cleaning. Open channels can be dug, or pipes can be directly connected to the regulating tank so that the water used to flush the flotation tank can be discharged.

4. The connecting pipe between the sewage inlet and the reaction tank needs to be as short as possible to prevent the floc from being destroyed in the pipe.

5. The clean water outlet can be connected to the sewer for discharge. If it needs to enter the next treatment process, it can be directly connected to the next treatment equipment.

6. The sludge outlet can be connected to a sludge tank or sludge treatment equipment.