1. Embedded rail steel embedded parts shall be embedded on the top of walls on both sides of the horizontal flow pool, one piece per meter. Anchor bolts and pins shall be made on both sides of each embedded part, which is conducive to pressing the rail firmly.
2. Lift the air flotation machine to the level flow birdsong stream, place the four traveling wheels on the rail, level the ground according to the reference point, and check the overall dimensions.
3. Rolling the cable and electrical installation, transfer the lifting cable to the galvanized steel wire rope with a hook, tighten the galvanized steel wire rope, and fix it on the vertical poles on both sides. Connect the main cable, plug in the power to adjust the walking condition, assemble the limit switch and contact block, and assemble the anti falling partition according to the key position of the return.
4. For trial operation, the air switch shall be operated continuously for at least 8 hours after the use is completed, and the driver shall be checked every minute to see if there is rail drop. Once found, it shall be stopped immediately to prevent the air flotation machine from falling into the pool.
5. Assemble the suction pump on the operation bridge.
6. For the construction of sludge suction pipe and sludge discharge pipe, gradually install the pipe and sludge suction nozzle from the inlet of the sludge suction pump from top to bottom. The distance between the sludge suction nozzle and the pool is 10-20mm. Several sludge suction pumps are summarized into one sludge outlet pipe and discharged into the sludge ditches on both sides of the horizontal flow tank.
7. Connect the switching power supply of the suction pump.
8. Water seepage test pump: after the test run of the air flotation machine is no problem, fill the pool with water. The water level is specified to be 30mm higher than the pump impeller of the sludge suction pump. Start the pump while entering the river, and observe the effluent condition of the sludge outlet.